En
Submit your application

“Unjustifiably acquired funds” and “advance payment” are different concepts

The Supreme Court of Ukraine, by a resolution on case No. 910/21154 / 17 of 15.02.2019, distinguished between the concepts of “advance payment” and “groundlessly acquired funds”!

Legal conclusion promulgated

Initially! One legal entity applied to the economic court with a claim against another legal entity to recover the prepayment amount under a contract for the manufacture of custom-made furniture.

The lawsuit was motivated by the fact that the contractor did not fulfill the obligations assumed (did not even try), therefore, must return the prepayment!

The court of first instance dismissed the claimant’s claims, referring to the fact that the customer had delayed the advance payment to the contractor, therefore, the latter did not violate the deadlines, since they lasted for the time of the prepayment delay.

The court also noted that the fact of untimely transfer of the advance payment is a violation of the terms of the contract by the customer!

The prescriptions of Articles 612, 613 of the Civil Code of Ukraine regarding this situation state that in this case the contractor does not have the obligation to perform the work on time, and the customer is canceled the right to unilaterally terminate the service contract and the right to demand the return of the prepayment.

The appeal court agreed with this decision!

This instance focused on the availability of a basic contractual deadline, including the one set by the parties for making an advance payment, which “corrects” in this situation the process of starting and completing work.

The deadline was violated by the customer, therefore, everything else automatically obeys this factor!

During the cassation hearing of the case!

“The customer pointed out to the Supreme Court of Ukraine that the courts of previous instances focused on finding grounds for the plaintiff’s refusal from the service contract in the context of Part 2 of Art. 849 CCU, but …

They ignored the prescriptions of Part 4 of Art. 849 of the Civil Code, which provides for the unconditional right of the customer at any time before the completion of the work to withdraw from the contract by paying the contractor for the amount of work performed and reimbursing him for losses caused by termination of the agreement. “

The customer also asked the cassation to pay attention to the following points:

  1. The reference of economic courts to the delay of the obligee’s obligation in a disputable legal relationship, as one of the grounds for refusing to satisfy the claim, is completely unfounded. This circumstance is important for determining the grounds for recovering losses for violation of the contract, but is not included in the subject of proof in the dispute over the return of the advance payment under the work contract.
  2. Unilateral cancellation of the contract under the law (Articles 651, 653, 849 GKU) does not need to be agreed with the defendant, since the disputable agreement has already been terminated from the moment the notice of termination of the contract was sent to the contractor, which was implemented by the plaintiff in the process of pre-trial settlement of the problem and this the moment was taken into account when developing a work contract.

The Ukrainian Supreme Court, analyzed the dispute and resolved it in favor of the plaintiff, “between the case” differentiating between the concepts of “advance payment” and “groundlessly acquired funds”!

06.02.2020

67

YOU MAY BE INTERESTED IN
Legal conclusion governing the donation of a share in a joint-stock company

The Grand Chamber of the Supreme Court of Ukraine, by its decision in case No. 909/1294/15 of 01.10.19, “annulled” the conclusion of the Supreme Court of Ukraine in case No. 33/45-09-1388 of 22.12.09, with the help of which the courts considered disputes on the donation of shares in these most societies to each other. Donating […]

Supreme Court of Ukraine on invalidation of the terminated agreement

Departure from existing legal positions by replacing them with new conclusions in the formation of law enforcement practice by the Supreme Court of Ukraine is a standard procedure! Thus, on November 27, 2019, the BC-SCU published a legal opinion in case No. 905/1227/17, by which it departed from the 2015 conclusion in case No. 918/144/15. […]

One of the reasons for non-execution of court decisions of the Russian Federation in Ukraine

So, in the analyzed case No. 334/5077/19, the Ukrainian court considered the person’s petition for recognition and granting permission to execute the decision of the court of Tula, adopted in 2018, on the territory of our country. The sanction was required to collect funds from the defendant (international debt collection). The Ukrainian court notified the […]

To Guarantors! Artificial insolvency is impossible!

A case won in court does not mean that the lender will automatically receive what the borrower owes him! One of the “worked out” schemes among the bank’s borrowers is that they alienate property at the stage of judicial review or during the period when the court decision comes into force. The main thing in […]

Supreme Court: debt collection and replacement of debtors in enforcement proceedings

The Grand Chamber of the Supreme Court of Ukraine has figured out the issue of who is legally obliged to pay off debts when replacing the original debtor with two – the main and subsidiary at the stage of execution of the court decision. “The replacement of the parties does not relieve anyone from responsibility, […]

SCU on the validity of the contract after the replacement of the 1st page in it

The impossibility of establishing certain circumstances does not relieve the participants in the process from the need to prove them! This conclusion was made public by the Supreme Court of Ukraine on 25.09.19 following the results of the proceedings in case No. 397/928/16-c. The reason for the dispute was the replacement of the first page […]